The performance task uses the location, roof inclination and orientation and shading information to estimate the annual output of the system. This is then used in the consumption task to estimate how much of what is generated will be used directly, used to charge a battery andor exported to the grid.grid which is needed to estimate the financial benefits of the system.
Navigating the performance task
The right hand sidebar contains options to switch between the sunpaths and the performance results:
As well as the following options
Update the location, pitch and orientation of the roofs and panel allocation |
|
![]() |
View all options including editing performance preferences and opening the help page |
Editing inputs
Certain inputs are required for the performance estimate to be calculated. Designing in 3D and configuring your settings to automate panel allocation and sunpath diagram calculations will streamline much of this task.
Location and roofs
First, if not already input when creating the project, you will need to set the location. If you are creating a flat roof system or using quick roof mode, you will also need to input pitch and orientation data. Both this and the location data are used to determine the output per kWp of the system.
Both the location and roofs section may show as ticked and completed already if this information can be pulled from earlier tasks in the project. The
Panel allocation
This section will depend on how you have configured your settings.
- If you have selected for your panels to be automatically allocated, then panel allocation will show as completed. If location and roofs are also already completed, then the modal will not open when opening the task.
- If you have selected suggest allocation then here you can choose to edit the allocation or select Done to close the modal.
- If you have manual allocation selected then you will need to allocate the panels here. Further information about manual panel allocation can be found below.
How do I manually allocate my panels?
- Select the current roof and inverter input from the lists on the left.
- Click or drag over panels to allocate them to an inverter input.
- When the right number of panels have been allocated, the text on the inverter input will show in green.
- Once all inverter inputs have the correct number of panels, all inputs will be in green and this message will show at the top.
Below all your inverters and roofs, you can then click next.
Additional things to note:
- All panels connected to an input must share the same pitch and orientation. Panels incompatible with the selected string will be be unselectable.
-
Use the
icon to reset the allocation on the inverter or individual inverter inputs.
- Below where it says Next, you also have the option to use auto-stringing.
If automatic allocation is selected and the location and roofs tabs are already completed, then the input window will not open,open. clickClick the pen icon to open the window.
Sunpaths
The sunpath diagrams are used to calculate the shading factor, or shading losses. The sunpath diagram maps the sun's movement across the sky for a specific location and time of year. Users can draw horizons on the diagram to indicate obstructions like trees or buildings.
The
or Howshading factor is the percentage of sunlight blocked by obstacles like buildings or trees. The sunpath diagrams are used to calculate the shading lossesfactor, calculated?
shading losses. For each point on the sun’s path, the system calculates:
Direct Radiation Loss: Thethe amount of sunlight blocked by thehorizon.horizon DiffuseandRadiation Loss: Thethe reduction in scattered sunlight due to obstructions.
Theseis lossescalculated areby combined with the frequency of the sun's position and physical factors (like air mass) to estimatecomparing the total impactavailable ofsolar shading.radiation The(from direct, diffuse and reflected radiation) to the amount that reaches the panel after shading is applied. If an obstruction blocks direct sunlight and reduces diffuse radiation, the shading factor representsincreases. the percentage of solar radiation reaching the panels after accounting for these obstructions.
Switching between inverters and inputs
On the top left you will see each of your inverters, below this for each inverter you will see each input on the inverter. A sunpath diagram is calculated for each input.
Automating with 3D
If designing in 3D mode, the shading can be calculated automatically, provided any obstructions have been modeled. Otherwise, you will need to manually draw on the sunpath diagram what shade is on the panels at different points in the year.
Performance results
Section A details all the installation data with the installed capacity, orientation of the system, inclination of the system and the location.
In section B, the section A data is used to generateestimate sectionthe output per kWp for the unshaded arrayB using the NREL's PVWatts calculator. The percentage of output lost from shade is then subtracted from this value before it's then multiplied by the kWp of the input, to calculate the estimated generation per input.
UK site: MCS self-consumption calculation
This process follows MCS guidelines defined in The Battery Standard MIS 3012 ISSUE 0.1 to predict self-consumption of the generated PV electricity. UK companies installing under MCS will need to provide this calculation.
We also have a more sophisticated self-consumption model available through our Consumption Task which you may like to provide customers in addition to the MCS calculation.
Enter the annual electricity consumption of the property
For the most accurate results use a value from past electricity bills. Or use an assumed value: the mean value for a domestic property in the UK is approximately 3500 kWh per year. The lookup tables for this calculation only permit values between 1500kWh and 6000kWh. Use the consumption task for more detailed consumption calculations or for values that fall outside this range
Select the occupancy archetype for the property
Properties that are occupied during the day will typically consume more PV-generated electricity directly. Properties that are empty during the day may benefit more from battery storage that can store PV-generated electricity for later use.
Is additional self-consumption anticipated from power diverters, electric space heating, electric water heating or electric vehicle charging?
You can enter any figure here, but the calculation assumes that a maximum of 95% of the generated electricity is available for self-consumption so the value in the results table will be capped to the remaining available generation capacity.